INTEGRAL ENGINEERING

INTEGRAL ENGINEERING

In the period 2015- 2020, the Contractor Integral Engineering engaged CEIM for the performance of the geotechnical terrain investigation works, geophysical tests, installation of inclinometers, laboratory tests, as well as geotechnical designing of several locations in Republic of Serbia, as following:
2015 – 2017: Performance of geotechnical investigations and tests along several sections of the new E-75 Highway of the Corridor X, Section: Carichina Dolina – Tunnel Manajle, LOT 5 (route and bridges);
2016: Designing of two retaining walls (D6 and D7) with height larger than 14 m for stabilization of the cutting Kucajska Dolina (chainages: km 891+095 – km 891+300 and km 891+625 – km 891+778). Е-75 Highway of Corridor X, Section: Carichina Dolina – Tunnel Manajle’
2018 – 2020: Performance of geotechnical investigations and tests and installation and monitoring of inclinometers for rehabilitation of slopes no. 2, 3, 4 and 5 of the new Е-75 Highway of Corridor X, Section: Grdelica – Carichina Dolina, LOT 1: Gornje Polje – Tunnel Predejane (route and bridges);
2018: Performance of geotechnical investigations and tests for rehabilitation of landslide in the zone of the slope on chainage km 65+100 - 65+550 of the new E-80 Highway Nish – Dimtrovgrad, Section 5a: Chiflik – Stanichenje;
2018: Performance of geotechnical investigations and tests for rehabilitation of landslide in the zone of the tunnel Sarlah on chainage km 72+250 – 72+510 of the
new E-80 Highway Nish – Dimtrovgrad.